How permit fees are calculated
We do not publish fee amounts anywhere on this site. They are set by local ordinance, revised without notice, and a stale figure in a directory is worse than no figure at all. What we can do is explain how the number is built, so you can read your jurisdiction's own fee schedule properly and recognise when a quote is missing something.
The components
Almost every permit invoice in the United States is assembled from some subset of these.
- Base permit fee. A flat charge for small, defined scopes; above a threshold it usually becomes a sliding scale tied to declared valuation.
- Plan review fee. Commonly a fixed percentage of the base fee — often somewhere between a quarter and two-thirds of it — charged whenever drawings need examination.
- Trade permits. Electrical, plumbing and mechanical are normally separate permits with their own fees, not inclusions in the building permit.
- Zoning or planning review. Applies when footprint, height, use or lot coverage changes.
- Impact or capacity fees. Charged on new dwelling units and new commercial floor area to fund roads, schools, water and parks. On a new house these frequently exceed the permit fee several times over, and they are the line item people most often fail to budget for.
- Technology or records surcharge. A small percentage funding the permit system itself.
- State surcharge. Some states levy a per-permit charge that the local office collects on the state's behalf.
- Reinspection fee. From the second visit onward when work fails or is not ready.
- After-hours inspection fee. A premium rate for inspections outside normal hours.
- Work-without-permit penalty. Commonly a doubling of the permit fee, sometimes more.
Valuation is the number that matters most
Where fees scale with valuation, the declared project cost drives everything downstream. Declare it accurately and include labour as well as materials, even when you are doing the work yourself — most jurisdictions require a labour value to be imputed. Offices maintain valuation tables based on square footage and construction type, and they will correct a declaration that falls below them. An under-declaration discovered later can be treated as a misrepresentation rather than an error.
Why the invoice comes in above the schedule
Three explanations cover most cases. Trade permits were quoted separately and you read only the building permit line. Surcharges are listed apart from the headline fee rather than inside it. Or the valuation was revised upward at review.
When fees are due
Most jurisdictions invoice at issuance rather than at submission, and some split it: a plan review fee at intake, the balance at issuance. This matters for cash flow on larger projects, and it is worth asking at the counter rather than discovering it.
Refunds
Refund policies are narrow. Plan review fees are usually non-refundable once review has begun, because the work has been done. Permit fees are sometimes partially refundable if the permit is withdrawn before any inspection. Ask before you withdraw rather than after.
Never pay a permit fee through a third-party site. Pay the jurisdiction directly, through the portal or counter it operates. If a site offers to "handle your permit" for a fee, you are paying a middleman for something you can do yourself, and the office will still need to deal with you directly.
Questions people ask about this
How much does a building permit cost?
There is no national answer, and any site giving you one is guessing. Fees are set by local ordinance and vary by permit type, declared valuation and jurisdiction. Read your jurisdiction's published fee schedule — every jurisdiction page on this site links to it where one is published.
Are permit fees refundable if I cancel?
Partially, sometimes. Plan review fees are generally not refundable once review has started. Permit fees may be partially refundable before any inspection occurs. Ask the office before withdrawing.
Why do I need separate electrical and plumbing permits?
Because they are inspected separately by different inspectors against different code chapters. The building permit covers structure and the overall project; trade permits cover the systems.
What happens to the fee if my application is rejected?
Plan review work already performed is normally retained. If the application is rejected at intake as incomplete, before review, most offices will not have charged the review fee yet.
This guide describes how permitting generally works across the United States. Requirements, thresholds and penalties are set locally. Find your jurisdiction for its official source.